Conjet’s High Speed Tunnel Repairs


Current Digital Issue

Click to read.

Archives

April 2026
March 2026
February 2026
January 2026

  1. More Archives >>

    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021

    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    October 2014
    September 2014
    July 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013

Conjet’s High Speed Tunnel Repairs

Published June 2015

top-pic

 

The Belgian railway operator, Infrabel, ur-gently needed to repair defective concrete in the Biéreau tunnel just south of Brussels. Hydrodemolition with a Conjet Robot 365 was used to selectively remove the damaged and decaying concrete at record speed.

The 875m long, 10.5m diameter Biéreau tunnel forms part of the 4.4km long, dual Line 161D railway track linking the cities of Ottignies and Louvain-la-Neuve, 34km south of the Belgian capital Brussels. It was opened in 1975, and during its nearly 40 years of service, the tunnel’s concrete skin had deteriorated and parts were falling off. It needed urgent repairs and Infrabel has invested more than 4 million in the tunnel’s restoration.

photo1Closing the tunnel completely was not possible due to public transport demands in the urban area. So, it was decided the only option was to restore the tunnel in two sections and working and repairing the concrete from one track while trains passed by slowly on the other line. The restricted space and necessary safety and environmental precautions were critical considerations for the overall renovation project, which had to be completed in just 220 days.

Due to these restrictions, the restoration contractor BAGECI, a regional branch of industrial Belgian Group CFE, opted for the hydro-demolition technique, which uses a very high-pressure waterjet to selectively remove the defective concrete from the walls and roof. BAGECI bought a Conjet Robot 365 with a multipurpose arm and a specially-adapted feed beam, carrying the cradle and jetting lance, to fit the curvature of the tunnel wall. Conjet’s representative in Belgium, BPC International, sold the hydrodemolition equipment. The company was also responsible for service, support, and spare parts supply to guarantee 24-hour productivity and availability of the Conjet robot.

A 500kW Hammelmann S1200-48 high-pressure water pump and the Conjet Robot were installed on flat-bed rail wagons fitted with foldable, protective walls. This allowed the hydrodemolition and restoration work to be completed on one side of the tunnel while trains could safely pass on the opposite track.

photo2“Due to the special safety and environmental demands and lack of space, hydrodemolition was really our only option from the very start,” said BAGECI tunnel project manager Luc Bosmans. “We thought it was going to be the most productive method for this tunnel work, and it proved to be very efficient.”

In total, the Conjet Robot 365, together with the Hammelmann pump operating up to a pressure of 1200bar, worked 1370 hours in the Biéreau tunnel and selectively removed 1610m3 of defective concrete from the tunnel circumference at an average depth of 80mm to 100mm. The total area treated was approximately 17,000m2.

BAGECI also removed the concrete debris, damaged rebar, and applied new, high quality concrete on the tunnel lining. “This restoration has been completed in 220 days with the Conjet Robot demolishing and removing concrete at a rate of about 1.35m3/h. In my opinion, this is an excellent result,” said Bosmans.

photo3“Throughout the tunnel, the concrete has been harder and more resistant in some places, but with the auto regulation, the Conjet Robot selectively demolished and removed only the damaged concrete to the right depth over the entire surface,” said BAGECI site manager Sandro Bonsiambiante. “Another advantage was the high availability of the equipment. There is a lot of environmental dust and wear and tear on equipment in this kind of application, and the spare parts supply has been excellent with no serious break downs.”

The Conjet Robot 365 consists of a carrier that includes pulse-monitored drive wheels, electric and hydraulic systems, and a simple, easy-to-use control system. The carrier can be equipped with optional attachments, such as standard feed beam, tower, or a rotor assembly and can also be operated by a wireless control. The cutting head features a ±45° attack angle of the jetting lance as standard, variable oscillation width, and encoders for lance turning and cradle position.