Cleaning Transformers


Current Digital Issue

Click to read.

Archives

April 2026
March 2026
February 2026
January 2026

  1. More Archives >>

    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021

    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    October 2014
    September 2014
    July 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013

Cleaning Transformers

Published July 2015

top-pic

Photos courtesy of Jim Pasternak, NorthEast PowerWashing

 

The ladder to heaven that Jacob saw in a dream is the stuff of good thoughts. A high-voltage traveling arc, which is sometimes called Jacob’s Ladder, is not.

 

So serious a hazard is an electric arc that the Occupational Safety and Health Administration (OSHA) has a specific standard (1910.269(1)(6)) for fire resistant (FR) clothing. The “269” standard requires the training of workers in electric arc hazards, and it prohibits the use of clothing that might exacerbate an injury if an arc emerged at a worksite.

When Jim Pasternak and two of his team members took on the job of washing two new transformers at a substation, they were given FR clothing to wear; and they were under the watchful eye of a representative of the substation the entire time they worked. Pasternak owns NorthEast PowerWashing in Marlborough, CT.

The repertoire of Pasternak’s seven-year-old company encompasses such standard residential and commercial cleaning as house washes, decks, building exteriors, and heavy equipment. But there are several unique projects on the roster, too.

“One interesting job leads to another,” says Pasternak. And the cleaning of the transformers was perhaps the most interesting to date. Pasternak explains he did not go out seeking work at a substation. Instead, he was approached by the company that owns the facility. “They were impressed with our website,” he says. “They contacted us.” It was straightforward from there: “They had us walk the site. I gave them an estimate.”

Although Pasternak had never worked at a substation, he had every confidence his company could handle the job. The clarity of the substation management, particularly “the ease of working with them” contributed to that confidence.

So why did a transformer—two transformers, actually—have to be cleaned? The transformers had recently arrived from China. They had some dust and dirt on them—nothing extraordinary—and they each had some weld marks around their bases.

“This was definitely a unique situation because you would never clean the ones that were already in service,” says Pasternak. Yet even though the transformers were not in service, they were relatively close to transmission lines and other transformers on the substation site. It was a 350 kV substation. The two transformers that were being replaced by the new ones were each 50 years old.

Precautions of many sorts had to be taken. “All the trucks had to be grounded,” says Pasternak. “We had to wear special fire resistant (FR) clothing.” And because the distances between the new transformers and active parts of the station were so small, a lift could not be used.

Technically, the distance between the two new transformers and the live parts of the substation (125 feet and 50 feet, respectively) were great enough to accommodate the required lift distance of 30 feet, but the substation on-site supervisor determined there would be no lifts used.

“We had to be careful of the wind,” says Pasternak. The job had to be done in weather conditions where there would not be a concern about spray being carried on the wind. Even on a still day, the goal was to create no spray. Pasternak’s team used high flow at no more than 500–600 psi with a 0-degree tip and 4.0 orifice. Around the base of each transformer, a turbo nozzle was used.

Having cleaned water towers, Pasternak knew that weld marks were not always removable. Generally, though, as with the transformers (and water towers), the plan would be to paint following cleaning and any residual marks would be covered.

Sodium hypochlorite solution was used as the cleaning agent. Once the weld marks were removed from the base of the transformers, the transformer bases were going to be painted.

Each of the two new transformers—approximately 25-ft. square—had been positioned to the place it would reside at the substation. They had not been filled with oil. It took Pasternak and the two men on his team one day to wash both transformers. The effort required 1,500 gallons of water, and the team hauled in 500 gallons at a time.

“We usually get one or two unique jobs a year,” says Pasternak. For instance every six months, his team cleans a 300-ft. long, 16-ft. wide, slow-moving conveyor. Steam is used to clean the conveyor that moves mattresses. (Over time, debris accumulates on the conveyor.)

When Pasternak spoke with us in early May, he was just about to begin another job for the mattress company owner. He would be cleaning the small filters and grilles that are part of the large, rooftop cartridges tied to the heating, cooling, and ventilation system.

Whatever the project, explains Pasternak, completing it to the owner’s specifications is the surest way to find a path to the next project. And some of the next projects will fit in the unusual category.